Roof sheathing is complete
Metal stud framing is nearing completion.
Curb and gutter work is 90 percent complete.
What's next?
Shingles are arriving next week.
Fascia is scheduled to start next week. Fascia board is mounted where the roof shingles will overhang the eaves.
What's ongoing?
Rough-in of electrical and plumbing.
Workers are installing conduit and electrical boxes in the walls for wires pulling which will occur later. Drains, vents and water piping are also being placed inside the walls for future installation of fixtures. All these activities must occur before sheetrock is installed.